Everything so far has been the machine described at rest. This chapter runs it — one real epic, #1623 · platform-trading-hardening, followed through every ceremony step with the actual artefacts, which are preserved intact in examples/epic-walkthrough/. Dates and issue numbers are real; only the domain vocabulary is renamed. Read this chapter with the artefacts open — each section header links its primary source.

The story also contains the book's best moment, so it is worth flagging in advance: midway through, the verification machinery catches a defect in itself, and the response to that is the whole method in miniature.

The morning: a gap analysis becomes a PRD

July 2nd, 11:25 UTCPRD.md.

The trading backend was functionally mature: lifecycles shipped, RBAC shipped, outbox, contract tests, BDD suites. The epic began with a gap analysis run against the as-built code rather than the docs, asking what separates "works" from "enterprise-ready." The answer became a PRD stating five failure classes — and note the framing rule it sets for itself: each gap is stated as the failure mode, not as a list of endpoints that exhibit it, because "the fix has to be the cross-cutting mechanism, not a sweep of call sites":

  1. A broken feedback loop — a downstream context published a contract-defined event; nothing consumed it, so state never advanced and the contexts drifted.
  2. Concurrency unsafety — an availability check with no lock lets two writers jointly exceed a shared quota; no version column means silent lost updates; no idempotency key means a retry duplicates records.
  3. Unsafe redelivery — at-least-once delivery into consumers with no inbox ledger.
  4. Data-governance gaps — physical deletes on some endpoints, none on others.
  5. Contract infidelity — filters, a derived status, commands and export that the contract defines and the API doesn't serve.

Ten user stories, fifteen functional requirements, each requirement carrying Gherkin scenarios with concrete worked examples — a two-writer race on one quota, a version 3-vs-4 stale write, a reused idempotency key. Those scenarios are not documentation; in three steps they will become the RED suite. The PRD even flags a time-honesty principle in passing, about debt carried on an assumption: "debt with a correctness consequence needs a date, not an assumption."

The architecture pass: three decisions, made once

11:36 UTCarchitecture.md.

/pm:arch-create answers the questions the PRD deliberately left open, and its decision matrix separates inherited constraints (outbox convention, Redis cache-only, per-schema isolation — not re-debated) from the three genuinely new choices, each becoming an ADR:

  • ADR-0066 — quota serialization via PESSIMISTIC_WRITE on the source rows in deterministic order (not an advisory lock, not the deferred saga — which stays the long-term target, now with its debt note amended).
  • ADR-0067 — optimistic locking with MikroORM's native version column, version in the mutation DTO, mismatch → 409 STALE_WRITE. Declared a platform-wide convention, not a local fix.
  • ADR-0068 — inbox processed_event + idempotency_key + parked_message as per-service PG tables, the inbox insert transactional with the state change; the DLX demoted to transport backstop. Also platform-wide.

The document then goes further down than most architecture docs dare: naming conventions (table shapes, error codes, metric families), module structure per service, and an FR→file map. That depth is what lets ten parallel task agents later produce code that looks like one person wrote it.

The epic and its ten tasks

11:30–11:45 UTCepic.md, task files 16241633.

The epic's strategy line deserves quoting because it is the quiet reason the whole thing stayed tractable: "maximally reuse-driven: every new capability extends an existing, shipped mechanism rather than introducing a new one." The consumer mirrors an existing consumer; soft delete reuses the tenant filter's mechanism; filters reuse a shipped parser; audit reuses the activity recorder. Ten tasks, T1–T10 — tests first (T1), production verification last (T10), nine parallelizable, one deliberately sequential. Each task file carries acceptance criteria cross-referenced to PRD Gherkin, a Definition of Done thirteen checkboxes long, and its depends_on / conflicts_with edges — which will matter shortly.

The hinge: sixty tests that must fail correctly

11:46 UTCtest-manifest.md.

/pm:tests-generate produced the RED suite: 28 files — 10 Gherkin features, 88 step definitions, 9 testcontainers specs, 5 unit stubs, one message-pact — 60 test cases in all. The manifest's defining feature is its "RED reason" column: every file documents why it fails, and the reasons are engineered, not incidental. Two distinct RED mechanisms are used deliberately:

  • Import-RED — the spec statically imports a module that does not exist yet (invoice-processed.handler), failing at collection. Proof the implementation is absent.
  • Behavior-RED — the spec drives real, existing code and asserts the future behavior: two genuine em.fork() racers against today's unlocked availability check; a stale write that today silently succeeds, asserted to reject. Proof the current behavior is what the PRD says it is.

The distinction is verification craft: an import-RED can only tell you code is missing; a behavior-RED pins down what the system does now, so the GREEN flip later means exactly one thing. And writing the specs against the contract paid immediately — it surfaced that an existing endpoint returned a different error code and HTTP status than the contract specifies. A drift only a test written from the contract could catch; it entered T4's scope on the spot.

The gate: a CRITICAL that refused to be waved through

11:48 UTCreadiness-report.md.

/pm:readiness-check — an independent checker, not the epic's author — audited the package: a 15-row FR-coverage matrix (every FR covered by an implementation task plus T1's tests plus T10's verification — "no single-touchpoint FRs"), twelve validation checks, findings by severity. It found one CRITICAL: the epic's BDD scenarios were not yet on disk (generation was in flight). The report's handling of it is the ceremony's character in one line:

Resolution path: wait for landing + independent verification; this report will be updated and the verdict flipped to READY. Do NOT override.

And the flip, when it came at 12:19, was earned, not assumed — the frontmatter records what "independently verified" meant: file counts matched the manifest, zero existing test files modified, the five import-RED targets confirmed absent, and both services' typechecks failing with exactly the expected missing-module errors and nothing else. Verdict: READY — 0 CRITICAL, 1 MAJOR (example-maps lagging, mitigated, ~1h fix recommended into T1), 5 MINOR, each with an owner and a timing.

Sync, and the plan meets the graph

20:00 UTCgithub-mapping.md, execution-status.md.

/pm:epic-sync created issue #1623 with real child issues #1624–#1633. Then execution planning did something quietly sophisticated: it read the tasks' conflicts_with edges and graph-coloured them into waves:

flowchart LR
    subgraph w0["Wave 0"]
        t1624["#1624<br/>RED baseline"]
    end
    subgraph w1["Wave 1 — mutually non-conflicting"]
        t1625["#1625 write-back<br/>PILOT"]
        t1626["#1626 inventory<br/>idempotency"]
        t1627["#1627 quota<br/>serialization"]
        t1629["#1629 soft delete<br/>+ audit"]
        t1630["#1630 list<br/>contract fidelity"]
    end
    subgraph w2["Wave 2 — solo"]
        t1628["#1628 safe mutations<br/>conflicts with 3 of Wave 1"]
    end
    subgraph w3["Wave 3 — solo"]
        t1631["#1631 command<br/>completeness"]
    end
    subgraph w4["Wave 4"]
        t1632["#1632 observability"]
    end
    subgraph w5["Final"]
        t1633["#1633 prod-verify<br/>+ 48h soak"]
    end

    t1624 --> w1 --> t1628 --> t1631 --> t1632 --> t1633

    t1628 -.->|conflicts| t1627
    t1628 -.->|conflicts| t1629
    t1631 -.->|conflicts| t1629
    t1631 -.->|conflicts| t1630
    t1632 -.->|depends on| t1625

Dotted edges are the conflicts_with declarations; the waves are what falls out once you respect them. #1628 and #1631 each conflict with three of their neighbours, so they run alone — a scheduling fact derived from the task files, not a judgement call made at 6pm. — five mutually non-conflicting tasks in Wave 1; #1628 alone in Wave 2 (it conflicts with three);

1631 alone in Wave 3; observability after its dependencies; prod-verify last. The

status file also records a judgment call against the default tooling:

Epic-start's "all agents in ONE shared branch" is unsafe here: 5 conflict edges + git-add races. Using per-issue worktrees, merged sequentially.

That is chapter 6's scar tissue (the git-add race memory) changing an execution plan in real time.

The pilot — and the day the tests were wrong

July 2nd evening → July 3rdexecution-status.md, 1625.md.

Wave 0 landed the RED baseline (#1624): dependencies installed, RED verified — typecheck failing on exactly the four missing-implementation modules. Then #1625, the inbound write-back consumer, ran as the Wave 1 pilot, and the pilot did what pilots are for: it surfaced three systematic defects in the RED baseline itself

  1. Wrong SQL placeholder dialect — raw conn.execute calls used PostgreSQL's $1 placeholders where MikroORM needs ?. Four files affected.
  2. A broken step-expression escape/api inside Cucumber expressions, where / is the alternation operator, aborted the entire BDD suite at load. The bug also existed in a previously merged file — meaning the BDD suite had not been gating CI and nobody knew.
  3. A fixture that failed itself — a seed helper's default left a row in DRAFT while the scenario asserted CONFIRMED, so the test failed on its own setup rather than on the missing behavior it existed to specify.

Every layer of the method shows up in how this was handled. The three defects were fixed in a dedicated remediation commit to the baseline, so every later task inherits a clean RED. The no-regression proof was empirical: the full integration run's failure set was re-checked against the baseline commit and shown identical. One of the three ("$1 vs ?") was initially mis-ruled fine by the reviewing lead and corrected by an empirical run — recorded without embarrassment, alongside the memory-tree lesson it minted: "run the test, don't overrule empirical with static." And the episode produced a permanent upgrade to the ceremony itself:

RED verification lesson: typecheck-only is insufficient — must RUN testcontainers.

This is the point of the whole apparatus, stated by accident. The RED suite is the measuring instrument for everything downstream; the pilot calibrated the instrument before nine parallel tasks trusted it. A process that cannot catch its own defects just propagates them at machine speed.

1625 itself finished verified green by independent re-run: testcontainers 3/3,

pact 9/9, 517 unit tests passing, 86 BDD scenarios loading with the write-back scenarios green — and one scenario correctly stopping at a pending('009') metric step, because that assertion belongs to task #1632 and the suite says so. Even the incompleteness is typed.

What the walkthrough is for

The export freezes the epic at this moment — pilot proven, waves planned, baseline clean — which is the right freeze-frame: every ceremony artefact exists, and the remaining tasks are repetition of a now-calibrated loop. Read the artefacts in this order and you will have watched the entire method work once:

Order Artefact What it shows
1 PRD.md verifiable requirements, Gherkin with worked examples
2 architecture.md inherited vs decided; the three ADRs
3 epic.md reuse-driven decomposition into ten tasks
4 test-manifest.md the RED suite and its engineered failure reasons
5 readiness-report.md the independent gate, and a CRITICAL done right
6 github-mapping.md state synced to real issues
7 execution-status.md wave planning, the pilot, the baseline remediation
8 1624.md1633.md what a task spec looks like when an agent will execute it

Next: the pilot ran one maker at a time. The remaining question of scale — many agents inside one task, many workstreams on one machine — is machinery of its own. Chapter 12 — Running many at once →